The Columbiana City Council has selected a company to complete its $1.8 million downtown revitalization plan.

In a special meeting on Monday night, the council accepted the low bid of R.E. Grills Construction Company Inc. of Shannon, Ala., for the project which will include a round-about to handle traffic flow around the old county courthouse as well as sidewalk and street light improvements down Main Street.

Grills’ bid $1.8 million for the base project. The city did not accept options for an irrigation system or a one-year maintenance contract.

The only other bid meeting the city’s requirements was from Walker Patton Company Inc. of Birmingham. That bid came in at $1.9 million.

Grills’ $80,000 bid for the irrigation system and $14,000 for the maintenance contract

were not accepted. Walker Patton bid $35,000 for the irrigation

and $15,000 for the maintenance contract.